Mathrafal has been a successful farm for generations and has diversified over the last two decades. A set of the old farm buildings have been converted to modern office space. They are well-lit with some of the old roof timbers on view so you get a sense of their age. They have a high level of insulation and a heated, polished concrete floor. The site has a hydro-electric scheme, a very large photovoltaic array and a biomass boiler with oil backup.
We designed and installed the underfloor heating system for the second phase of the office development. The heating is fed from 9 manifolds, drawing energy from a small secondary buffer tank (TML), with a weather-compensator blending valve (LK).
In the original plant room, we made a series of changes to the pipework to allow the boilers to run more efficiently, and added cascade control for the boilers. In the phase 1 office block, we installed a low-loss header to eliminate conflicts between the phase 1 and phase 2 transfer pumps.
The tenants of the phase 1 development were kept warm throughout the work on the phase 2 block, although we did have to arrange a schedule for shutting down the boilers for the work in the original plant room.